Post by captain scarlet on Oct 31, 2013 2:01:24 GMT
looking good so far
|
|
|
Post by UK RUSS 1960 OLDS on Nov 4, 2013 21:38:57 GMT
Hi Guys,
Will try and update with a few pics tomorrow.
Building regs have inpected it now and i can finally get the base poured, i guess it is going to take about 16 cubic meters or there abouts.
Hoping to get it done in the next couple of days.
Cheers.
Russ.
|
|
|
Post by UK RUSS 1960 OLDS on Nov 5, 2013 8:54:23 GMT
Hi Guys, A couple of pics from last week, Cheers. Russ.
|
|
|
Post by UK RUSS 1960 OLDS on Nov 5, 2013 8:54:52 GMT
|
|
|
Post by UK RUSS 1960 OLDS on Nov 5, 2013 8:55:44 GMT
Hi Guys, Put together a make shift ramp so i can get the cars and the van out of the back garden just before the garage goes up. Cheers. Russ.
|
|
|
Post by Nojive55 on Nov 5, 2013 9:37:52 GMT
Coming on well whens the grey suff going in..
Bob.........
|
|
|
Post by UK RUSS 1960 OLDS on Nov 5, 2013 9:44:37 GMT
Hi Bob,
Waiting on a call at the moment, problem is getting the mix to the back of the garage, looking like a pump is the best option but that is another £400+. Needs to be done this week as the garage is being made at the moment.
Cheers.
Russ.
|
|
|
Post by UK RUSS 1960 OLDS on Nov 11, 2013 10:30:42 GMT
Hi Guys, A few pics from last week. Spent Monday to Thursday sorting out the concrete options for the oversite, levelling all the ground out around the outside of the garage, getting all the rubbish that was along the fence behind the transit out into the front yard ready for disposal. Opted for the even more expensive self levelling concrete in the end, although this option was £200 more than the pump option it came with two bods that specialise in laying it so was more cost effective in the end plus only half the work with four of us. First load in, Cheers. Russ.
|
|
|
Post by UK RUSS 1960 OLDS on Nov 11, 2013 10:36:03 GMT
Hi Guys, Second load in.........was hoping we could do it in two loads, but we were about 2 1/2 meter's short. Cheers. Russ.
|
|
|
Post by UK RUSS 1960 OLDS on Nov 11, 2013 10:42:26 GMT
Hi Guys, Third load 2.5 cu meteres just to finish it off, levelled out, then sprayed with a sealant to stop it drying out too quickly, the idea behind this is to stop any cracking as the concrete goes off. Cheers. Russ.
|
|